Kohteen tiedot
We carried out the refurbishment of the Anaesthesia and Surgery Unit K at Jorvi Hospital, completing the project on schedule in 2023. The refurbishment covered the anaesthesia and surgical department, the Heart Centre and laboratory facilities, as well as all required temporary facilities. In total, the project comprised approximately 10,500 gross floor square metres.
The K Unit performs abdominal, endocrine, plastic and burn surgery, orthopaedic and trauma procedures — more than half of which are emergency surgeries.
Successful delivery required close cooperation and continuous dialogue with the client. The project was demanding, as all work was carried out within a fully functioning hospital, further challenged by the pandemic period. These challenges were overcome with the experience and expertise of our team.
Hospital operations remained uninterrupted throughout
The hospital continued its normal activities during construction, requiring meticulous planning and minimisation of disruptions. All work was carried out safely inside an active hospital environment, with particular attention to patient safety and continuity of care. The new theatres now support all patient groups and ensure modern, high-quality conditions for surgical services.
“The work had to be carried out with exceptional care, safely and with full consideration for hospital operations”, says Tomi Virolainen, Project Manager at HUS Kiinteistöt Oy.
Expertise in demanding hospital environments
This complex project enabled us to apply our extensive experience from similar healthcare and specialised facility projects. The project proceeded and was completed as planned, with hospital staff kept well informed at every stage.
“The project stayed on schedule and within its original budget, and despite challenges such as the exceptional pandemic period, we succeeded thanks to close cooperation between HUS, SRV and the designers”, Virolainen says.
A trusted partnership with HUS
The refurbishment of Jorvi Hospital’s K Unit continues the long-standing and successful cooperation between SRV and HUS. Together we have delivered several major projects — including the construction of Siltasairaala, the largest hospital building project in HUS's history. Our collaboration has been successful, fostering mutual trust and enabling continued partnership.
View our references